Preparation of completion Reports
After completing the electrical installation works of a new HV/EHV installation or making additions to an existing HV/EHV installation, the electrical contractor who carried out the installation works shall conduct the necessary pre-commission checks and tests and prepare the completion report in the prescribed format. The completion report shall be signed by the electrical contractor and the owner of the installation and submitted to the Electrical Inspectorate and the supply authority. A model form ofthe completion report is given at the end of this chapter.
The completion report shall necessarily contain the following details
1. Full name plate details of all electrical machines and equipments covered in the completion report.
2. Test results of main equipments and switch boards.
3. Measured values of earth resistivity at the site before commencing and after completing the installation.
4. Test results of protective relays
5. Test results of insulating oil in the case of all oil containing equipments.
Copies of the following documents shall accompany the completion report.
1. Power allocation from the supplier
2. Sanction under Sec.44 of Electricity (Supply) Act 1948 in the case of generators
3. Approval from the Electrical Inspectorate.
On receipt of the completion report, the Electrical Inspector will inspect the installation and carry out such additional tests as may be found necessary. If the installation is found fit for energisation, the Electrical Inspector will issue the sanction for energisation under R.63 of the IE Rules. Commencement of supply to a new installation is made by the supplier on the basis of the sanction for energisation issued by the Electrical Inspector.
After satisfactory commissioning of an electrical installation, the date of energisation and date of commercial operation shall be intimated to the Electrical Inspectorate department and the electricity Supply authority. In the case of major equipments, the manufacturer of the equipment may also be intimated of the test results and the date of energisation.
Form of Completion Certificate
I/We certify that the installation detailed below has been installed by me / us and tested and that to the
best of my/our knowledge and belief, the installation complies with the provision of IER 1956 and
also IS 3043, IS-732 and other relevant codes of practice for electrical installations.
1. Name of installation
2. Voltage and system of supply
3. Particulars of work and test results
(a) Transformers (Give details of each transformer)
· Rating
· Voltage
· Make
· Serial number
· Year of manufacture
· Results of Insulation Tests
· Results of earth resistance and continuity tests
· Results of other relvant tests depending on the voltage level and rating of the transformer
(b) Generators (Give details of each Generators)
· Rating
· Voltage
· Make
· Serial number
· Year of manufacture
· Results of Insulation Tests
· Results of earth resistance and continuity tests
· Results of other relvant tests depending on the voltage level and rating of the
Generator
(c) H.V motors
· Number of motors
· Name plate details of each motor
· Result of insulation tests
· Result of earth resistance and continiuity tests
· Results of other relvant tests depending on the voltage level and rating of the Motors.
(d) M.V Motors
· Number of motors
· Name plate details of each motor
· Results of insulation tests
· Results of earth resistance and continuity tests
(e) EHV and HV cables (Give details of each cable)
· Length of cable and number of terminations/joints
· Results of Insulation Tests
· Result of H.V withstand test result
· Results of earth resistance and continuity tests
· Results of other relevant tests
(f) M.V cables
· Results of Insulation resistance tests
· Results of Earth resistance and continuity tests
(g) Relays
· Results of Relay and control wiring tests
· Results of tests of protection and measurement CTs
· Results of tests of PTs
(h) Protective earthing
· Earth resistivity at the site
· Earth resistance of individual earth electrodes
· Result of earth continuity test
· Combined earth resistance of the installation
(i) Special Equipments
· Name plate details of each equipment
· Results of insulation tests
· Results of earth resistance and continuity tests
· Results of other relevant tests depending on the voltage and rating of the equipment
Signature of the Supervisor
Signature of the owner
Signature of the Contractor
Name and address with permit number of the Supervisor.
Nameand address of the owner
Name and address with Contract Licence number of the Contractor.